Welcome to this week’s project update from Bexley Garden Rooms, covering progress for the week commencing 16 March 2026.
Lots of new projects started this week and a couple of large ones finally completed. Thankfully, the rain has held off to give our teams a welcome break from getting soaked!
- Sidcup garden office constructed in 5 days. Now ready to be plastered, final fix electrics, floor and skirting laid and finished with a coat of paint.
- Greenhithe 7m x 3.5m multi-function room now completed and looking great!
- Bexleyheath conservatory replacement ready to be plastered, final fix electrics, toilet installed, flooring laid and painted.
- Studio (5.4m x 4.8m) in Hither Green well under way with ground screw foundations, frame up, first fix electrics, PIR and rockwall insulation and ready for doors to be fitted and plastered this week.
- Bexley garden office started with padstones added to an already existing concrete base, frame built and insulation added.
- Bexleyheath 7.5m x 4m multi-purpose room started with ground screw foundations, frame up and first fix electrics.
- Erith 7m x 4.5m garden office started.