Welcome to this week’s project update from Bexley Garden Rooms, covering progress for the week commencing 8 December 2025.
We are still very busy, ensuring all our current builds are completely finished in time for Christmas.
This week our teams have:
- Plastered, laid the flooring and skirting and completed second fix electrics on the Welling build we are doing following a fire.
- Clad and boarded the Sissinghurst entertaining room ready to be plastered next week.
- Laid the floor, completed second fix electrics and finished the canopy and under area on the Bexley garage conversion.
- Boarded and plastered the garden gym in Chislehurst.
- Plastered, clad and prepared the bar ready to be installed next week on a garden room in Orsett.
- Painted the walls and prepared the floor on our new showroom build in Bexley Village.